West Branch Panther Creek watershed Plan

What is the West Branch Panther Creek Plan?

The Illinois Natural Resources Conservation Service (IL-NRCS) in conjunction with the project sponsor, the Village of Roanoke, IL, will be developing a Watershed Plan/Environmental Assessment (Plan/EA) for the West Branch Panther Creek Watershed in 2024-2026.

The Plan/EA will analyze opportunities to reduce recurring flooding along the West Branch Panther Creek through structural and/or non-structural alternatives.

The Village of Roanoke, IL is providing assistance with alternative development and site selection for this plan. Structural alternatives may include adjustments to the runoff and streamflow channels near Roanoke. Non-structural alternatives may include wetland creation, restorations, or enhancements.

Watershed Plan Map

Track progress and stay informed with our interactive map, providing real-time updates on the West Branch Panther Creek Watershed Plan.

Completed Public Meetings

Initial Public Meeting

January 22, 2025
2pm Central Time

Village Hall meeting room

Download Meeting Slides

Download Presentation Slides

Watch Meeting Recording

Final Public Meeting

December 18, 2025
6pm Central Time

Village Hall meeting room

Download Meeting Slides

Watch Meeting Recording

Project Schedule

NRCS / Village of Roanoke

Public / Agencies

Green rightward arrow

Sept 2024 – June 2025

Scoping

  • Draft Public Participation Plan, Public Meeting Notice, and Agency Letters.

    Begin Phases of the Watershed Planning Process

  • Phase I - Identify Flood Risk Areas

  • Phase II - Determine Objectives

  • Phase Ill - Inventory Resources

  • Phase IV - Analyze Resource Data

  • Phase V - Formulation Alternatives

  • Provide comments on the proposed action, alternatives, issues, and impacts to be in the Draft Plan/EA

  • Attend Initial Public Jan 22, 2025

We Are Here

July 2025 – Aug 2026

Draft Plan/EA

Green right-pointing arrow
  • Phase VI - Evaluate Alternatives

  • Phase VII - Propose Flood Risk Alternatives

  • Phase VIII - Draft Environmental Assessment and Circulate for Review

  • A Draft Plan/EA is developed that presents, analyze, and compares the potential environmental impacts of the proposed action and alternatives.

  • The Draft Plan/EA goes under multiple stages of review by NRCS.

  • A Notice Of Availability is then published in the Federal Register and a 30 day public comment period on the Draft Plan/EA begins.

  • Provide Comment. Public comments are considered in the preparation of the Final Plan/EA

  • Attend Final Public Meeting (December 18, 2025)

Sept 2026 – Nov 2026

Final Plan/EA

Green right-pointing arrow
  • A Final Plan/EA is prepared and distributed.

  • Responses to public comments on the Draft Plan/EA aro included in the Final Plan/EA

  • Track progress on Project Website

Dec 2026

Record of Decision

  • The Final Plan/ EA is submitted to NRCS National Headquarters for authorization.

  • After the Final Plan/EA is published, a minimum 30 day waiting period is required before a Record of Decision (ROD) can be issued.

  • The Notice Of Availability (NOA) Will be published in the Federal Register, notifying the public of the decision NRCS made on the proposed action.

  • No action can be taken until the decision has been made public.

  • View Final Plan/EA & Record of Decision

FAQs

We compiled a list of commonly asked questions about this Project. This section is designed to provide additional background information on flood mitigation and ecological restoration, the benefits and how we need your input to help create a more sustainable future for the West Branch Panther Creek Watershed Community.  If you have a question or concern that is not covered here, please reach out to us by clicking on the contact form at the bottom of the page.

How to Comment

On December 20, 2024, IL-NRCS announced a public scoping period to consider opportunities for flood risk reduction within the West Branch Panther Creek Watershed Plan. There are several ways to submit comments to have your voice heard.  All comments received through February 2026 will be considered and included in the public record as part of the development of the Draft Plan/EA.

  1. Watch recording of the Initial Public Meeting from January 22, 2025

  2. Watch recording of the Final Public Meeting from December 18, 2025

  3. Use the Public Scoping Feedback and Comment Form below

Lead Agency Contact

Aaron Pryer
Illinois NRCS Acting Watershed Program Manager
217-353-6633
aaron.pryer@usda.gov

Primary Consultant

Baird/Stantec JV